Long Creek Incised Channel Beaver Mimicry Project:
Client: Montana Chapter | The Nature Conservancy
The designs called for structures with an expected life span of 6 – 10 years and solely utilized building materials sourced on site, (gravel, screen cobble, donor wetland sod).
Construction occurred in 2014 and 2016. A total of 18 mimicry structures were installed that affected 4.75 miles of linear channel and activated over 10,000 feet acres of formerly disconnected floodplain channels.
Record runoff in April 2016 tested the first series of installed structures and follow-up monitoring and indicated no significant damage.
The average structure cost was approximately $4,000.
Incised Channel Restoration Pilot Project
Demonstration of Hardened Riffle Construction J-L Ranch 2014